This section applies where—
on the ground that all or part of the work to which the application or notice relates is higher-risk building work.
The person intending to carry out the work may appeal to the appropriate national authority, before the end of the prescribed period, on the ground that none of the work is higher-risk building work.
Building regulations may make provision about appeals under this section, including in particular provision—
The provision that may be made by virtue of subsection (3)(a) includes provision about—
The decision made on the appeal is final (subject to subsection (6)).
The appellant or the local authority may, before the end of the prescribed period and with the permission of the High Court, appeal to the High Court against the decision of the appropriate national authority on a point of law.