This section applies where a renewables obligation order contains banding provision.
The order may provide for the effect of any banding provision made in an earlier order, or of any provision of a pre-commencement order, to continue, in such circumstances as may be specified, in relation to—
For the purposes of subsection (2) "pre-commencement order" means an order made under section 32 before the coming into force of this section.
Subsection (6) applies to a generating station in respect of which a statutory grant has been awarded if—
The requirements specified under subsection (4)(b) may relate to the time when the grant was awarded (whether a time before or after the coming into force of this section).
A renewables obligation order which contains banding provision may provide for the operation of that provision in relation to electricity generated by a generating station to which this subsection applies to be conditional upon the operator of the station agreeing—
If the grant in respect of which an amount falls to be paid under paragraph (a) or (b) of subsection (6) was paid by the Scottish Ministers, the references in those paragraphs to the Secretary of State are to be read as references to those Ministers.
For the purposes of subsection (6)—
and, for the purposes of provision made under that subsection, a renewables obligation order may make provision about the cancellation of an award of a statutory grant or an instalment of such a grant.
In this section "statutory grant" means—
This section is without prejudice to section 32K(1)(b) (power for renewables obligation order to include transitional provision and savings).