This section applies for the purposes of sections 32LE, 32LG and 32LI.
The grid or radar delay condition is met in respect of an onshore wind generating station if, on or before the date on which the Authority made its decision to accredit the station, the documents specified in subsection (4), (5) or (6) were—
The grid or radar delay condition is met in respect of additional capacity if, on or before the date on which the Authority made its decision that the additional capacity could form part of an onshore wind generating station, the documents specified in subsection (4), (5) or (6) were—
The documents specified in this subsection are—
The documents specified in this subsection are—
The documents specified in this subsection are—
In this section "the primary date" means—