Section 3E: Binding decisions of the Agency for the Cooperation of Energy Regulators and of the European Commission

Electricity Act 1989 · 1989 c. 29View on legislation.gov.uk

Part I: ELECTRICITY SUPPLY

The Authority must carry out its functions under this Part in the manner that it considers is best calculated to implement, or to ensure compliance with, any binding decision of the Agency or the European Commission made under the Electricity Directive, the Electricity Regulation or the Agency Regulation (or the predecessor of the Electricity Regulation or the Agency Regulation) in relation to electricity.

For the purposes of subsection (1), a binding decision does not include a decision that is not, or so much of a decision as is not, assimilated law.

About this text

This legislation text comes from legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. These source and reuse terms cover the legislation text, not Remedy's commentary.

Reuse reviewed 21 August 2026 under Open Government Licence v3.0.