Where the Secretary of State or the council of a London borough is satisfied—
the order may provide for the stopping up or diversion of the highway during such period as may be prescribed by or under the order and for its restoration at the expiration of that period.
Where a competent authority within the meaning of section 257 are satisfied—
the order may provide for the stopping up or diversion of the footpath , bridleway or restricted byway during such period as may be prescribed by or under the order and for its restoration at the expiration of that period.
Without prejudice to the provisions of section 247 or 257, any such order as is authorised by subsection (1) or (2) may contain such provisions as appear to the Secretary of State , the council of the London borough or the competent authority (as the case may be) to be expedient—
and any provision included in the order in accordance with subsection (4) of section 247 or subsection (2) of section 257 requiring payment to be made in respect of any cost or expenditure under the order may provide for the payment of a capital sum in respect of the estimated amount of that cost or expenditure.
In relation to any highway which is stopped up or diverted by virtue of an order under section 247 or 248, sections 271 and 272 shall have effect—
and sections 275 to 278 shall have effect accordingly.
Subsection (4) shall not apply to land constituting the site of a highway in respect of which opencast planning permission (within the meaning of section 51 of the Opencast Coal Act 1958) has been granted.