This section applies if the appropriate authority appoints a person to carry out or hold a qualifying procedure.
A qualifying procedure is—
Where a local planning authority cause a qualifying procedure to be carried out or held, the appropriate authority is—
Where the qualifying procedure is an independent examination of a strategic development plan under section 64 of the Planning and Compulsory Purchase Act 2004, the appropriate authority is the Welsh Ministers.
The appropriate authority may require the whole or any part of the costs borne by it in relation to the qualifying procedure to be paid by the local planning authority or corporate joint committee causing the qualifying procedure to be held.
The appropriate authority may cause the amount of any such costs to be certified; and any amount so certified and required by it to be paid by a local planning authority or corporate joint committee shall be recoverable from that authority or committee as a civil debt.
What may be recovered under this section by the appropriate authority is the entire administrative cost of, or incidental to, the qualifying procedure , so far as borne by it , including, in particular, such reasonable amount or element as it may determine in respect of the general staff costs and overheads of his department.
For the purposes of subsection (4), the appropriate authority may by regulations prescribe a standard daily amount in relation to any description of qualifying procedure and any description of person appointed to hold it, . . . and where, in relation to a qualifying procedure of that description, a person of that description is or has been so appointed, what may be recovered in respect of that qualifying procedure by virtue of the appointment of that person . . . is—
The cost of, or incidental to, a qualifying procedure which does not take place may be recovered by the appropriate authority from the local planning authority or corporate joint committee from which it would have been recoverable, had the qualifying procedure taken place, to the same extent, and in the same way, as the cost of, or incidental to, a qualifying procedure which does take place.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
A reference to a local planning authority or corporate joint committee causing a qualifying procedure to be carried out includes a reference to the case where under the Planning and Compulsory Purchase Act 2004—
In this section—
This section applies in relation to costs arising before, as well as costs arising after, its coming into force.