If, at a time when an initial notice is in force, it appears to the registered building control approver that some or all of the work has become higher-risk building work, the registered building control approver must, as soon as is reasonably practicable, cancel the relevant part of the initial notice by notice in the prescribed form given to—
If, at a time when an initial notice is in force, it appears to the person carrying out or intending to carry out the work that some or all of the work has become higher-risk building work, the person must, as soon as is reasonably practicable, cancel the relevant part of the initial notice by notice in the prescribed form given to—
Where a person is required to give a notice under subsection (1) or (2) in relation to higher-risk building work in England, the person must, as soon as is reasonably practicable, give a copy of that notice to the regulator.
If, at a time when an initial notice is in force, it appears to the local authority concerned that some or all of the work has become higher-risk building work, the authority must cancel the relevant part of the initial notice by notice in the prescribed form given to—
Where a local authority is required to give a notice under subsection (4) in relation to higher-risk building work in England, the local authority must give a copy of that notice to the regulator.
A person commits an offence if they fail without reasonable excuse to—
A person guilty of an offence under subsection (6) is liable on summary conviction to a fine.
Where a notice is given under any of subsections (1), (2) and (4) (a "cancellation notice")—
In this section "the relevant part of the initial notice" means so much of the initial notice as relates to work that has become higher-risk building work.