This section applies where any land has been acquired by a Minister, a local authority or statutory undertakers under Part IX of this Act or under Chapter V of Part I of the Planning (Listed Buildings and Conservation Areas) Act 1990 or Chapter 5 of Part 3 of the Historic Environment (Wales) Act 2023 or compulsorily under any other enactment or has been appropriated by a local authority for planning purposes, and—
If the acquiring or appropriating authority is satisfied that the extinguishment of the right or, as the case may be, the removal of the apparatus is necessary for the purpose of carrying out any development with a view to which the land was acquired or appropriated, they may serve on the operator of the electronic communications code network a notice—
The operator of the electronic communications code network on whom a notice is served under subsection (2) may, before the end of the period of 28 days from the date of service of the notice, serve a counter-notice on the acquiring or appropriating authority—
If no counter-notice is served under subsection (3)—
If a counter-notice is served under subsection (3) on a local authority or on statutory undertakers, the authority or undertakers may either—
If a counter-notice is served under subsection (3) on a Minister—
In this section any reference to the appropriation of land for planning purposes shall be construed in accordance with section 246(1) as if this section were in Part IX.
For the purposes of this section the relevant period, in relation to a notice served in respect of any right or apparatus, is the period of 28 days from the date of service of the notice or such longer period as may be specified in it in relation to that right or apparatus.