If a person makes an application in accordance with section 74B to a local planning authority, the authority may by notice in writing to the person—
Those matters are—
The local planning authority may make a determination under subsection (1)(c) only if the person who made the application has agreed in writing to the terms of the determination.
A modification under subsection (2)(a) must not prohibit construction activities from being carried out at any time when they are permitted to be carried out under the condition or approved document as it had effect when the application was made.
A date determined under subsection (2)(c) must not be later than 1 April 2021.
Subsection (7) applies if the local planning authority does not give notice under subsection (1) before the end of the period of 14 days beginning with the day after that on which the application in accordance with section 74B was sent to the authority.
The condition or approved document to which the application relates is deemed to have been modified in accordance with the application.
If the local planning authority makes a determination under subsection (1)(c) about only some of the matters specified in subsection (2), the condition or approved document is deemed to have been modified in accordance with the application in respect of the other matters specified in subsection (2).