This section applies in relation to outline planning permission granted or deemed to be granted—

in relation to the development of land in England, and
subject to a condition which has the effect that all or a part of the development to which the permission relates must be begun not later than a time falling within the period—
beginning with the day on which section 18 of the Business and Planning Act 2020 comes into force, and
ending with 31 December 2020.

The condition is deemed to provide instead that the development or (as the case may be) the part of the development must be begun not later than 1 May 2021.

The time by which the development or (as the case may be) the part of the development must be begun is not to be extended to a later time than that for the time being provided for in subsection (2).

The reference in subsection (1) to outline planning permission granted, or deemed to be granted, subject to a condition which has the effect mentioned in paragraph (b) of that subsection includes a reference to the permission being subject to a condition which has that effect by virtue of being subsequently modified.

In this section "outline planning permission" has the meaning given by section 92(1).

About this text

This legislation text comes from legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. These source and reuse terms cover the legislation text, not Remedy's commentary.

Reuse reviewed 21 August 2026 under Open Government Licence v3.0.