This section applies in relation to outline planning permission granted or deemed to be granted—
If an approval under this section ("an additional environmental approval") is granted, or deemed to be granted, in relation to the outline planning permission—
A person with an interest in the land or a person acting on behalf of such a person ("the applicant") may make an application to a local planning authority in whose area the land is situated for an additional environmental approval in relation to the outline planning permission.
The application must—
The local planning authority must, by notice in writing to the applicant, grant, or refuse to grant, the additional environmental approval in relation to the outline planning permission before the end of the period of 28 days beginning with the day after that on which the application in accordance with subsection (4) was sent.
If the local planning authority fails to do so, the additional environmental approval is deemed to be granted in relation to the outline planning permission.
The applicant and the local planning authority may agree in writing one or more extensions to the period mentioned in subsection (5), but the period may not be extended by a total of more than 21 days.
The local planning authority is to grant the additional environmental approval in relation to the outline planning permission if and only if—
The EIA requirement is met if, at the time the local planning authority is deciding the application—
The habitats requirement is met where, if a decision were being taken as to whether to grant the outline planning permission at the time the local planning authority is deciding the application—
An additional environmental approval may not be granted subject to any condition.
No additional environmental approval is to be granted or deemed to be granted after 31 December 2020, unless it is granted on an appeal in respect of which the notice under section 78(3) is served on or before that date.
A person who makes an application under this section is to be taken to have agreed—
In discharging its functions under this section, a local planning authority must have regard to any guidance issued by the Secretary of State.
The reference in subsection (1) to outline planning permission being granted, or deemed to be granted, subject to a condition which has the effect mentioned in paragraph (b) of that subsection includes a reference to the permission being subject to a condition which has that effect by virtue of being subsequently modified.
In this section—
"European site" and "European offshore marine site" have the same meaning as in the Conservation of Habitats and Species Regulations 2017 (S.I. 2017/1012);
"outline planning permission" has the meaning given by section 92(1).